01How long does planning permission take for an extension?
In England, the statutory determination period for a valid non-major planning application is normally eight weeks unless a longer period is agreed. Preparation and validation happen before or around that period, and actual authority performance varies.
02How long do extension drawings take?
A measured survey and concept design may take roughly four to eight weeks for a straightforward project. Planning drawings and technical drawings are separate stages, and revisions or complex coordination increase the programme.
03How long does Building Regulations approval take?
Technical design commonly takes four to eight weeks before or alongside submission. GOV.UK says a Full Plans decision is normally expected within five weeks, or two months with consent, but queries and project complexity can affect progress.
04How long does a single-storey extension take to build?
A straightforward single-storey extension may take around 12–20 weeks on site. Larger openings, kitchens, difficult access, drainage or internal remodelling can move it beyond that range.
05How long does a two-storey extension take?
Many two-storey extensions require roughly 20–32 weeks or longer for construction. Roof integration, bathrooms, structural work and disruption to the existing house materially affect the sequence.
06Can planning and Building Regulations be prepared at the same time?
They can overlap, particularly where planning risk is low and time is important. Developing technical information before planning approval creates a risk that later planning changes require technical redesign.
07When should I contact builders?
Early conversations can test availability and buildability. Comparable prices should normally be sought once coordinated drawings, structural information and specification are sufficiently developed.
08Can I live in my house during the extension?
Often, but loss of a kitchen or bathroom, dust, noise, security, utility interruptions, children, pets and home working should be considered against the cost and programme impact of temporary accommodation.
09What is the most common cause of delay?
There is no universal single cause. Late decisions and changes are especially disruptive because they affect design, approvals, procurement and construction rather than one isolated stage.
10How far in advance should I appoint an architect?
For many projects, beginning six to twelve months before the desired construction start is sensible. Complex planning, Party Wall procedures, consultant lead times or busy contractors may require longer.